Santa Ynez Transfer Station Project: Efficiency and Precision in Industrial Construction
Client
Santa Ynez
Project type
Industrial
MOC, Inc.’s involvement in the Santa Ynez Transfer Station project highlights our capability in handling complex industrial construction tasks.
This project included:
- Demolition of existing slab and stabilizing wet soil encountered during the process.
- Subgrade compaction and installation of dowel baskets.
- Pouring high-early concrete that achieved a PSI of 3,500 in just 18 hours.
- Round-the-clock work over 48 hours, ensuring zero downtime and project efficiency.
The project showcases our proficiency in rapid construction techniques and our commitment to meeting tight deadlines.